Ballyclare High School, Ballyclare - Education

Ballyclare High School

Mechanical Services Installation including modification of existing boilerhouse plant and controls. Plumbing & heating installation to the following blocks - General, sports, technology, dining, languages, art. Installation of sports hall ventilation system.  Installation of new fume cupboards.

 Value  £380,000
 Scope of work  Mechanical Services Installation
 Special features  Phased erection of new blocks whilst keeping existing school and    services functioning.
 Timescale  75 weeks
 Architect

 M. C. Logan

 Client  North Eastern Education and Library Board
 Consulting Engineers  NEELB
 Main Contractor  Blackbourne McCombe Ltd (Karl Construction)